Bertram Road Bridge Replacement Project

◄ Back
December 28, 2021 8:11 AM

Bertram Road Bridge Update:

The project was let on December 22, 2021 and was awarded to Peterson Contractors Inc. (PCI) of Reinbeck, Iowa for a cost of $2,425,608.45. The contract specifies a late start date of April 3, 2023. This means the contractor may begin on or before that date. An exact start date is not known at this time, but I assume it will begin in the Fall of 2022. Once started, the contractor will be allowed 100 working days to complete the project. The road will be closed to all traffic during construction and the project will take approximately 5-6 months for completion.

Facebook Twitter Email

Latest Update:

October 6, 2023 3:34 PM

The majority of the work is complete and Bertram Road, Berry Road and Wilder Drive are now open to all traffic. The old blue truss bridge has been moved to the new site at the Indian Creek Nature Center where it is currently being worked on the incorporate into their trail system.

Please contact me with any questions.

Curtis Logan ([email protected])

Prior Updates

View All Updates
August 29, 2023 8:12 AM

Progress continues on the Bertram Road Bridge Replacement project. The contractor has now paved the north portion of Bertram Road. Entrances and intersections remain to be paved as well as reconstruction of the trail. The project is approximately 80% complete.

Please contact me with any questions.

Curtis Logan ([email protected])

July 20, 2023 11:17 AM

The contractor began placing concrete on Berry Road and Bertram Road south of the bridge. The concrete cannot be driven on for a minimum of 48 hours. Homeowners along this portion may have difficulty accessing their property for this period of time.

Please contact me with any questions.

Curtis Logan ([email protected])