Hollenbeck Road Bridge Replacement Project

◄ Back
December 28, 2021 8:12 AM

Hollenbeck Road Bridge Update:

The project was let on December 22, 2021 and was awarded to Taylor Construction of New Vienna, Iowa for a cost of $1,362,266.58. The contract specifies a late start date of June 13, 2022. This means the contractor may begin on or before that date. The contractor will be allowed 90 working days to complete the project. The road will be closed to all traffic during construction and the project will take approximately 4-5 months for completion. An exact start date is not known at this time.

Facebook Twitter Email

Latest Update:

October 24, 2022 7:25 AM

Construction on the bridge is complete. The road is now open to traffic.

Please contact me with any questions.

Curtis Logan ([email protected])

Prior Updates

View All Updates
August 24, 2022 8:25 AM

Construction continues on the bridge over Bear Creek on Hollenbeck Road. Hollenbeck Road remains closed. Construction is expected to be completed in mid-October.

Please contact me with any questions.

Curtis Logan ([email protected])

May 25, 2022 10:10 AM

Construction on the Hollenbeck Bridge over Bear Creek has begun. Hollenbeck Road is now closed and a detour is in place. The project is expected be completed sometime in August or September. 

Please contact me with any questions.

Curt Logan ([email protected])