April 12, 2022 2:53 PM
Lefebure Road Project Update:
The project was let on April 12, 2022 and was awarded to Metro Paver of Iowa City, IA for a cost of $2,240,189.25. The project includes an 8” concrete overlay from Wright Brothers Blvd north to Linn Street in Fairfax. The project also includes the replacement of the box culvert immediately south of the Southview Road intersection. The contract specifies an approximate start date of June 1, 2022. This means the contractor will begin around that date. An exact start date is not known at this time. Once started, the contractor will be allowed 70 working days to complete the project. The road will be closed to through traffic during construction.