Jordan's Grove Road Grading Project

◄ Back
June 29, 2022 8:59 AM

Jordans Grove Road Project Update:

The project was let on April 19, 2022 and was awarded to Boomerang Corp. of Anamosa, Iowa for a cost of $1,959,886.00. The contract specifies a late start date of July 5, 2022. This means the contractor must start the project before that date. Once started, the contractor will have 75 working days to complete the project. The contractor has set a tentative start date of July 5th.

Facebook Twitter Email

Latest Update:

November 29, 2022 5:32 PM

We've received multiple phone calls regarding the surface of Jordan's Grove Road.  We are aware of the condition and we will blade it regularly and monitor the condition closely.  It is holding moisture right now and should be in better condition once it has a chance to dry out. 

Thank you to all those who called our office to inform us. 

Garret Reddish