Boy Scouts Road Bridge Deck Overlay Project

◄ Back
February 7, 2023 2:08 PM

Boy Scouts Road Bridge Deck Overlay Project Update:

The project was let on January 18th, 2023 and was awarded to PCI Roads, LLC of St. Michael, MN for a cost of $263,623.25. The contract specifies a late start date of August 14, 2023. This means the contractor may begin on or before that date. The contractor will be allowed 25 working days to complete the project. The road will be closed to all traffic during construction and the project will take approximately 3-5 weeks for completion. An exact start date is not known at this time.

Facebook Twitter Email

Latest Update:

September 11, 2023 3:22 PM

The contractor has completed most of the work at the bridge and Boy Scouts Road is now open to all traffic. There will still be some minor cleanup work and misc. items, so please continue to use caution.

Please contact me with any questions.

Curtis Logan ([email protected])

Prior Updates

View All Updates
August 21, 2023 10:02 AM

Work continues on the Boy Scouts Road bridge in Waubeek. As a reminder the bridge is closed to all traffic and a detour is in place. The contractor is activily chipping out concrete making large holes and exposing rebar. Please respect the road closure signs and do not try to drive though the construction site.

Please contact me with questions.

Curtis Logan ([email protected])

August 7, 2023 2:50 PM

The contractor has started work and Boy Scouts Road is now closed. There is a detour in place.

Please contact me with any questions.

Curtis Logan ([email protected])