Austin Road Bridge Repair

◄ Back
March 9, 2021 9:35 AM

Austin Road Bridge Repair Update:

The project was bid on March 2, 2021 and was awarded to Taylor Construction, Inc. of New Vienna, Iowa for a cost of $35,016.00. The project consists of repairing the timber bridge on Austin Road over East Indian Creek. The contract specifies a completion date of April 16, 2021. This means the contractor must complete the work on or before that date. Once started, the project will take approximately 2-3 weeks for completion. The contractor has not provided a start date at this time. The road will be closed to all traffic during construction.

To receive detailed project updates, go to www.linncounty.org and select the ‘Get Notified’ icon. Daily updates (or as work progresses) via email or text will be sent once work has started. You will need to create a free account for this service and select which projects you would like to be notified of. Please contact our office if you need assistance with this service.

Facebook Twitter Email

Latest Update:

April 9, 2021 8:35 AM

The bridge repair on Austin Road immeidatley west of Highway 13 is now complete. Although the bridge is now open, the Iowa DOT has closed Austin Road at Highway 13 due to their project.

Garret Reddish ([email protected])

Prior Updates

April 5, 2021 9:27 AM

As planned, Austin Road was closed this morning for bridge repair. The road is expected to remain closed for 1 week.

Garret Reddish ([email protected])

April 2, 2021 1:07 PM

The contractor plans to start on Monday April 5th. The project is expected to take 1 week.

Garret Reddish ([email protected])