Buffalo Valley Lane Bridge Replacement Project

◄ Back
April 13, 2022 11:22 AM

Buffalo Valley Lane Bridge Replacement Project Update:

The project was let on April 12, 2022 and was awarded to Peterson Contractors, Inc. of Reinbeck, Iowa for a cost of $276,329.75. The contract specifies a completion date of September 2, 2022. This means the contractor must have work complete on or before this date. An exact start date is not known at this time, but I assume it will begin in the summer of 2022. The road will be closed to through traffic during construction. A temporary stream crossing will be available for local residents. The project will take approximately 3-5 weeks for completion.