Hollenbeck Road Bridge Replacement Project

◄ Back
December 28, 2021 8:12 AM

Hollenbeck Road Bridge Update:

The project was let on December 22, 2021 and was awarded to Taylor Construction of New Vienna, Iowa for a cost of $1,362,266.58. The contract specifies a late start date of June 13, 2022. This means the contractor may begin on or before that date. The contractor will be allowed 90 working days to complete the project. The road will be closed to all traffic during construction and the project will take approximately 4-5 months for completion. An exact start date is not known at this time.

Facebook Twitter Email

Latest Update:

May 25, 2022 10:10 AM

Construction on the Hollenbeck Bridge over Bear Creek has begun. Hollenbeck Road is now closed and a detour is in place. The project is expected be completed sometime in August or September. 

Please contact me with any questions.

Curt Logan ([email protected])

Prior Updates

May 6, 2022 2:02 PM

The start date for the construction on the Hollenbeck Bridge over Bear Creek is now excepted to begin Monday May 23rd. Hollenbeck Road will be closed to all traffic once construction begins.

Please contact me with any questions. Thank you.

Curt Logan ([email protected])

May 4, 2022 7:45 AM

Construction on the Hollenbeck Road bridge over Bear Creek is tentatively planned to start on Monday May 16th.  Hollenbeck Road will be closed to all traffic when construction starts.  Construction is expected to last approximately 2-3 months. 

Please contact me with any questions. 

Curt Logan ([email protected]