Concrete paving on Ivanhoe Road from the City of Cedar Rapids limits to Jappa Road.

Facebook Twitter Email

Latest Update:

August 26, 2021 9:11 AM

Pavement markings are scheduled to be completed today.  The contractor still has to complete the western asphalt taper, touch up the ditches after the rain events, and place seed and mulch on the dirt.  Work should be completed over the next week or two. 

Garret Reddish ([email protected]

Prior Updates

View All Updates
August 18, 2021 11:29 AM

The contractor is currently placing shoulder rock.  The project is expected to be completed next week sometime. 

Please contact me with any questions. 

Garret Reddish ([email protected]

August 11, 2021 1:15 PM

As planned, the contractor started paving on Ivanhoe Road this afternoon.  The contractor will progress about a 1/4 today.  They will resume tomorrow and progress about a 1/2 mile.  They expect to finish on Friday.  As a reminder, you will not have vehicle access once paving passes by your entrance. 