Sawyer Road Box Culvert Replacement Project Update:

The project was let on March 29, 2022 and was awarded to Iowa Bridge and Culvert of Washington, Iowa for a cost of $492,883.25. The contract specifies a late start date of August 8, 2022. This means the contractor may begin on or before that date. An exact start date is not known at this time, but I assume it will begin in the summer of 2022. Once started, the contractor will be allowed 35 working days to complete the project. The road will be closed to all traffic during construction and the project will take approximately 1-2 months for completion.

Facebook Twitter Email

Latest Update:

August 9, 2022 7:16 AM

The contractor has begun construction on the project. Sawyer Road is now closed at the culvert and a detour is posted. The project is expected to be completed in late September or early October. 